Building and Anchors Photos

After many long days of working on the docks, three weeks of pouring concrete, and many many hours preparing for the construction of the building, we have made tremendous progress on all three projects!

The docks are complete.  We have a starting dock for the both the main cable and the Lil Bro, four exit docks and a walkway along the edge of the lake.  All other exit points will be along our floating docks around the main cable.

We have all our water anchors poured and two of our land anchors poured.  The land anchors weigh 46,000 lbs each!  We poured 74 concrete slabs to assemble the water anchors in just a few short weeks.  These towers aren’t going anywhere!

We have been preparing to begin construction on the building for a few weeks now and we finally broke ground this week.  We are currently working on the footers and the foundation and we will continue at an aggressive rate so it is ready for our Grand Opening on July 11!

I hope everyone is getting excited to wakeboard at Northeast’s first and only cable wake park this summer!

A special thanks to DiFiore Construction and F.G. Rayburn Mason Contractors for helping make this happen!

Foundation 1 Foundation 2 Docks Land Anchor Water Anchors